Planned Development Timeline

Bradshaw Aug2019
2009-2015
  • Exploration, permitting and economic study
2015
  • Published pre-feasibility study
2016
  • Received permits for bulk sample / advanced underground exploration
2017
  • Commenced site construction
  • Commenced ramp development
  • Purchased x-ray ore sorting technology
2018
  • Identified two high-grade gold zones
  • Executed agreement for sale of gold concentrate
2019
  • Renegotiated loan agreement
  • Executed toll-milling agreement
  • Raised C$12 MM
2019 – 2023
  • Care and maintenance
  • Complete bulk sample
2023
  • Engage Dumas-mine restart (April)
  • Engage Foraco-production mining (June)
  • Initiate exploration drilling (June)